Jon Michael Wyman
Design + Planning, LLC
A complete renovation to the credit union headquarters includes first floor office additions, new entrance
portal and drive-thru canopy with a second floor open work area. Interior spaces will be enlarged and
modernized with new private teller stations, handicap toilets and HVAC system. Exterior finishes include
ground face masonry, fiber cement panels and composite trim. Energy saving materials used are Icynene and
cellulose insulation, fiber cement products and reused doors and hardware. The new traffic and parking
layout will keep vehicles away from the front of the building, while providing two lanes for ATM and drive-up
service. Construction is scheduled from August through December 2008 with the credit union remaining
open during all phases of construction. This project is being done as project manager and clerk of the works.
Architect is Nicolai A. Calabro, AIA.
FRANKLIN FIRST FEDERAL CREDIT UNION, Greenfield Massachusetts
Schedule
12.1.08 Roofing and siding while interior work progresses.
11.24.08 Framing complete, on to the roof!
11.10.08 Second floor framing over the rear drive-thru continues.
11.3.08 Entry canopy framing complete, Rear drive-thru wood framing begins.
10.27.08 Second floor slab over the drive-thru poured, entry canopy framing begins.
10.21.08 Rear drive-thru backfilled and steel frame assembled.
10.13.08 Rear drive-thru excavated and foundations started.
10.6.08 Front addition foundations backfilled and framing begins.
9.29.08 Front additions excavated and foundations poured.
9.22.08 Construction continues in basement.
9.15.08 Construction to begin.
9.02.08 Building Permit granted.
8.25.08 Town of Greenfield Site Plan Review approved.
8.12.08 Architects permit package submitted to Town of Greenfield by Mowry & Schmidt, Inc.
8.04.08 Architects permit drawings, Chapter 34 Narrative and affidavits issued to Mowry & Schmidt Inc.
7.29.08 Architects site plan drawing submitted to the Town of Greenfield for review.
7.25.08 Bids reviewed and project awarded to general contractor, Mowry & Schmidt, Inc.
7.11.08 Project put out to bid.
7.03.08 Architects bid drawings complete.